NOV EXPANSION

Facility Type

Office / Warehouse Facility

Location

Conroe, TX

Size

70,000 sq ft

SiTe

5 acres

 

 

 

 

Overview

  • KDW designed/built a new Office and Warehouse facilty for NOV in Conroe, Texas.
  • The new expansion is located next to NOV’s Manufacturing Facility, reducing shipping costs and shipping delays.
  • 70,000 sq ft Pre-Engineered Metal Building.
  • Three (3) Overhead Cranes.
  • Five (5) Specialty Jib Crane Foundations.
  • 21,000 sq ft cement stabilized rock laydown yard.
  • The building design and power requirements allow for future expansion.

Need/Problem

  • NOV needed a new building constructed in the Conroe Business Park.
  • Time sensitive schedule.
  • The owner required racking be installed before the building was complete.

KDW Solution

  • KDW organized Pre-Construction meetings with subcontractors to ensure the timely finish date.
  • Owner meetings were held to follow up with the construction schedule.
  • KDW focused on the client’s need of installing the racking, ensuring the completion of that specific area of the building immediately.
  • The schedule from clearing the land to completion of the facility was finished in 5 months.

 

Fill out my online form.

NOV EXPANSION

Facility Type

Office / Warehouse Facility

Location

Conroe, TX

Size

70,000 sq ft

SiTe

5 acres

Overview

  • KDW designed/built a new Office and Warehouse facilty for NOV in Conroe, Texas.
  • The new expansion is located next to NOV’s Manufacturing Facility, reducing shipping costs and shipping delays.
  • 70,000 sq ft Pre-Engineered Metal Building.
  • Three (3) Overhead Cranes.
  • Five (5) Specialty Jib Crane Foundations.
  • 21,000 sq ft cement stabilized rock laydown yard.
  • The building design and power requirements allow for future expansion.

NEED / PROBLEM

  • NOV needed a new building constructed in the Conroe Business Park.
  • Time sensitive schedule.
  • The owner required racking be installed before the building was complete.

KDW Solution

 

  • KDW organized Pre-Construction meetings with subcontractors to ensure the timely finish date.
  • Owner meetings were held to follow up with the construction schedule.
  • KDW focused on the client’s need of installing the racking, ensuring the completion of that specific area of the building immediately.
  • The schedule from clearing the land to completion of the facility was finished in 5 months.